Register
One Richardson One Richardson
One Richardson

Stay up to date with the latest construction and project updates for One Richardson in South Perth. 

Project Construction Updates

The crane is up

Huge milestone this month with the crane being installed on site at One Richardson!

Construction activities completed

  • Suspended ground slab over fire tanks has been constructed
  • Crane base footing completed
  • Crane installation
Register Your Interest
One Richardson Construction Update September 2022
One Richardson Construction Update July 2022

Backfilling the basement

The construction team this month were busy carrying out the backfilling of the basement. The backfilling of a basement is an important step in the construction, providing vital structural stability, support to the basement walls and a barrier for external forces.

The team are close to finishing the backfilling to the basement, fire tanks, lift cores, the situ walls adjacent to the fire pump and potable water area

Register Your Interest

Preparation Work

The first two months of construction consisted of a lot of cleanup and preparation work including the fill importation and basement wall reinforcement. Once this initial phase is complete, we’ll start to see a few more exciting changes on site at One Richardson.

Construction activities completed

  • Fill importation
  • Installation of formwork and reinforcement to basement wall reinforcement
  • Slab on ground to Basement has been poured
  • Poring of raft footings is on-going
  • Reinforced walls to cores and fire tanks have been poured
Register Your Interest
One Richardson Construction Update June 2022