Stay up to date with the latest construction and project updates for One Richardson in South Perth. 

Project Construction Updates

Level 10 Vertical Structure Complete

In April, the building team was busy at the One Richardson construction site, with works including:

  • Level 9 and 10 concrete slab poured and the vertical structure completed.
  • Lightweight framed walls up to level 7 completed.
  • Internal painting up to level 5 completed.
  • And with window installation well underway.
  • Construction is progressing smoothly and the apartments are on track to be completed mid-late quarter 3 of this year.

    As One Richardson nears completion, it’s incredible to watch as the magnificent structure takes shape!

Register Your Interest
One Richardson_Construciton Update_Feb 2024

Upper Slab Pour to Level 10

Over the last few months, the construction team have been diligently making headway on a number of works:

  • Preparation for upper slab pour to level 10 is underway.
  • Installation of services first fix has commenced up to level 8 as the slabs are progressively poured.
  • Installation of internal stud/window framing and door frames trades have commenced and progressing up to level 7.
  • And the installation of external glazed sliding doors and windows to level 6 is now nearing completion.
  • One Richardson has almost entirely taken shape, a reminder that the final touches for these apartments are just around the corner.

    Stay tuned for more exciting updates coming soon!

Register Your Interest

Suspended Slab up to Level 8

Over the past two months, the construction team has been busy making headway on a number of works, including:

The completion of post tensioned suspended slab up to level 8, along with associated services prelays, as well as AFS installation up to level 7.

Furthermore, they are close to the completion of fire, hydraulics and electrical services installation up to level 6 as the slabs are progressively poured.

They have commenced internal stud framing, window framing, doors and painting trades installation, which has progressed up to level 6.

Finally, they are close to completion on the external glazed sliding doors and windows installation up to level 3.

Register Your Interest

Suspended Slabs Progress

September was a busy month for our team at the One Richardson development site.

Our team completed the suspended slabs and associated service prelays, along with AFS installation up to the 6th floor on the residential side of the development.

We commenced work on the suspended slabs for the Commercial Tower up to the 6th floor and the formworks to underside of the 7th floor.

Finally, we are close to completing the installation of fire, hydraulics and electrical services up to the 5th floor as we progressively pour the slabs.

Register Your Interest

Concrete poured on level 4

During May, our team completed the formwork for the slab levels and the floor cycle, and we are now in the process of pouring the concrete slabs.

This photo was taken last Saturday when the concrete was being poured on the commercial side of Level 4 looking across the Swan River.

The One Richardson building is taking shape as work on the construction site continues. It is beginning to resemble an apartment complex more and more.

Register Your Interest
One Richardson Construction Update May 2023

Slab levels

Progress on site at One Richardson is coming along and we’re now starting to see a building that looks like an apartment complex. Over the coming weeks, our team will be completing the formwork for the slab levels and the floor cycle will be a steady and repetitive process from here on out.

Colour palettes have now been selected and meetings have been scheduled for the final colour selections.

Register Your Interest

Siteworks are now complete

  • Site works are now complete.
  • Post tensioned suspended slab to residential first level deck is now installed.
  • Slab on the ground to commercial tower is currently underway.
  • Installation of AFS to the boundary neighboring walls is now complete.
  • Installation of concrete columns to the Ground Floor including reinforcement and formwork are 80% complete.
  • Installation of services is progressing, as the slabs are being poured.
Register Your Interest
One Richardson Construction Update February
One Richardson COnstruction Update January 2023

Ground level slab is complete

  • Earthworks is nearing completion.
  • Pouring of concrete slab on ground is complete.
  • Installation of AFS wall is progressing well.
  • Installation of reinforcement and formwork to concrete columns and first floor slab is progressing well.
  • Formwork to sheer walls to Ground Floor is complete.
  • Core to residential is complete up to Level 3.
  • Commercial core raft footing has commenced.
  • Dewatering is now complete.
Register Your Interest

Earthworks close to completion

  • Earthworks are close to completion, with the dewatering spears and equipment scheduled to be removed from site on 19 December 2022. This is a significant milestone for the project.
  • The pouring of concrete slab on the ground is progressing well.
  • Installation of AFS wall has commenced.
  • Installation of reinforcement to columns has commenced and progressing well.
  • Formwork to sheer walls to Ground Floor has commenced.
  • Core to residential is complete.
Register Your Interest
Construction Update November 2022
One Richardson Construction Update October 2022

Installation of ground services

  • Installation of in ground services pre-lay is close to completion
  • Tower crane and crane base is in place
  • Earthworks is on going
  • Pouring of concrete slab on ground has commenced
  • AFS has been supplied and stored on site
  • Installation of reinforcement to columns has commenced