Stay up to date with the latest construction and project updates for One Richardson in South Perth. 

Project Construction Updates

Internal Wall Sheeting

July was a productive month for the construction team, with the progress and completion of several works, including:

  • Internal Wall Sheeting up to Level 7 (100% complete).
  • Internal Wall Framing up to Level 7 (100% complete).
  • Internal Wall Framing Levels 8 – 13 (90% complete).
  • External Façade Cladding (90% complete).
  • Flooring & Painting Levels 3 – 6 (90% complete).
  • Service – Fire, Hydraulic & Elec (45% complete).
  • AFS Walls (95% complete).
  • One Richardson is steaming towards completion, and we are thrilled to see the building nearing its final stages.

    Keep an eye on this space for more updates coming soon!

Register Your Interest
One Richardson Construction Update July
One Richardson Construction Update June

Internal Wall Framing

June was a bustling month for the building team, as they made impressive strides on a multitude of works, including:

  • Suspended slabs up to L13 (100% complete).
  • Internal wall framing L8 – L12 (80% complete).
  • Internal wall sheeting L8 – L12 (70% complete).
  • External façade cladding (80% complete).
  • Painting Level 3 – Level 6 (90% complete).
  • Tiling Level 3 – Level 6 (60% complete).
  • The One Richardson project is gearing up to reveal its breathtaking views.

    Stay tuned for more exciting updates coming soon!

Register Your Interest

Suspended Slabs 100% Complete

May was a busy month for the building team, with them making headway on a vast number of works, including:

  • Suspended slabs (100% complete).
  • Painting Levels 3-6 (90% complete).
  • Tiling Levels 3-6 (40% complete).
  • Flooring Levels 3-6 (20% complete).
  • The team is working diligently to ensure all milestones are met, paving the way for the project to be completed within the projected timeframe.

    As we enter the final stretch, it’s exciting to watch One Richardson steadily taking shape, both internally and externally.

Register Your Interest

Level 10 Vertical Structure Complete

In April, the building team was busy at the One Richardson construction site, with works including:

  • Level 9 and 10 concrete slab poured and the vertical structure completed.
  • Lightweight framed walls up to level 7 completed.
  • Internal painting up to level 5 completed.
  • And with window installation well underway.
  • Construction is progressing smoothly and the apartments are on track to be completed mid-late quarter 3 of this year.

    As One Richardson nears completion, it’s incredible to watch as the magnificent structure takes shape!

Register Your Interest

Upper Slab Pour to Level 10

Over the last few months, the construction team have been diligently making headway on a number of works:

  • Preparation for upper slab pour to level 10 is underway.
  • Installation of services first fix has commenced up to level 8 as the slabs are progressively poured.
  • Installation of internal stud/window framing and door frames trades have commenced and progressing up to level 7.
  • And the installation of external glazed sliding doors and windows to level 6 is now nearing completion.
  • One Richardson has almost entirely taken shape, a reminder that the final touches for these apartments are just around the corner.

    Stay tuned for more exciting updates coming soon!

Register Your Interest
One Richardson_Construciton Update_Feb 2024

Suspended Slab up to Level 8

Over the past two months, the construction team has been busy making headway on a number of works, including:

The completion of post tensioned suspended slab up to level 8, along with associated services prelays, as well as AFS installation up to level 7.

Furthermore, they are close to the completion of fire, hydraulics and electrical services installation up to level 6 as the slabs are progressively poured.

They have commenced internal stud framing, window framing, doors and painting trades installation, which has progressed up to level 6.

Finally, they are close to completion on the external glazed sliding doors and windows installation up to level 3.

Register Your Interest

Suspended Slabs Progress

September was a busy month for our team at the One Richardson development site.

Our team completed the suspended slabs and associated service prelays, along with AFS installation up to the 6th floor on the residential side of the development.

We commenced work on the suspended slabs for the Commercial Tower up to the 6th floor and the formworks to underside of the 7th floor.

Finally, we are close to completing the installation of fire, hydraulics and electrical services up to the 5th floor as we progressively pour the slabs.

Register Your Interest

Concrete poured on level 4

During May, our team completed the formwork for the slab levels and the floor cycle, and we are now in the process of pouring the concrete slabs.

This photo was taken last Saturday when the concrete was being poured on the commercial side of Level 4 looking across the Swan River.

The One Richardson building is taking shape as work on the construction site continues. It is beginning to resemble an apartment complex more and more.

Register Your Interest

Slab levels

Progress on site at One Richardson is coming along and we’re now starting to see a building that looks like an apartment complex. Over the coming weeks, our team will be completing the formwork for the slab levels and the floor cycle will be a steady and repetitive process from here on out.

Colour palettes have now been selected and meetings have been scheduled for the final colour selections.

Register Your Interest
One Richardson Construction Update May 2023
One Richardson Construction Update February

Siteworks are now complete

  • Site works are now complete.
  • Post tensioned suspended slab to residential first level deck is now installed.
  • Slab on the ground to commercial tower is currently underway.
  • Installation of AFS to the boundary neighboring walls is now complete.
  • Installation of concrete columns to the Ground Floor including reinforcement and formwork are 80% complete.
  • Installation of services is progressing, as the slabs are being poured.