Project Construction Updates

Suspended Slab up to Level 8

Over the past two months, the construction team has been busy making headway on a number of works, including:

The completion of post tensioned suspended slab up to level 8, along with associated services prelays, as well as AFS installation up to level 7.

Furthermore, they are close to the completion of fire, hydraulics and electrical services installation up to level 6 as the slabs are progressively poured.

They have commenced internal stud framing, window framing, doors and painting trades installation, which has progressed up to level 6.

Finally, they are close to completion on the external glazed sliding doors and windows installation up to level 3.

Register Your Interest

Suspended Slabs Progress

September was a busy month for our team at the One Richardson development site.

Our team completed the suspended slabs and associated service prelays, along with AFS installation up to the 6th floor on the residential side of the development.

We commenced work on the suspended slabs for the Commercial Tower up to the 6th floor and the formworks to underside of the 7th floor.

Finally, we are close to completing the installation of fire, hydraulics and electrical services up to the 5th floor as we progressively pour the slabs.

Register Your Interest

Concrete poured on level 4

During May, our team completed the formwork for the slab levels and the floor cycle, and we are now in the process of pouring the concrete slabs.

This photo was taken last Saturday when the concrete was being poured on the commercial side of Level 4 looking across the Swan River.

The One Richardson building is taking shape as work on the construction site continues. It is beginning to resemble an apartment complex more and more.

Register Your Interest
One Richardson Construction Update May 2023

Slab levels

Progress on site at One Richardson is coming along and we’re now starting to see a building that looks like an apartment complex. Over the coming weeks, our team will be completing the formwork for the slab levels and the floor cycle will be a steady and repetitive process from here on out.

Colour palettes have now been selected and meetings have been scheduled for the final colour selections.

Register Your Interest

Siteworks are now complete

  • Site works are now complete.
  • Post tensioned suspended slab to residential first level deck is now installed.
  • Slab on the ground to commercial tower is currently underway.
  • Installation of AFS to the boundary neighboring walls is now complete.
  • Installation of concrete columns to the Ground Floor including reinforcement and formwork are 80% complete.
  • Installation of services is progressing, as the slabs are being poured.
Register Your Interest
One Richardson Construction Update February
One Richardson COnstruction Update January 2023

Ground level slab is complete

  • Earthworks is nearing completion.
  • Pouring of concrete slab on ground is complete.
  • Installation of AFS wall is progressing well.
  • Installation of reinforcement and formwork to concrete columns and first floor slab is progressing well.
  • Formwork to sheer walls to Ground Floor is complete.
  • Core to residential is complete up to Level 3.
  • Commercial core raft footing has commenced.
  • Dewatering is now complete.
Register Your Interest

Earthworks close to completion

  • Earthworks are close to completion, with the dewatering spears and equipment scheduled to be removed from site on 19 December 2022. This is a significant milestone for the project.
  • The pouring of concrete slab on the ground is progressing well.
  • Installation of AFS wall has commenced.
  • Installation of reinforcement to columns has commenced and progressing well.
  • Formwork to sheer walls to Ground Floor has commenced.
  • Core to residential is complete.
Register Your Interest
Construction Update November 2022
One Richardson Construction Update October 2022

Installation of ground services

  • Installation of in ground services pre-lay is close to completion
  • Tower crane and crane base is in place
  • Earthworks is on going
  • Pouring of concrete slab on ground has commenced
  • AFS has been supplied and stored on site
  • Installation of reinforcement to columns has commenced
Register Your Interest

The crane is up

Huge milestone this month with the crane being installed on site at One Richardson!

Construction activities completed

  • Suspended ground slab over fire tanks has been constructed
  • Crane base footing completed
  • Crane installation
Register Your Interest
One Richardson Construction Update September 2022
One Richardson Construction Update July 2022

Backfilling the basement

The construction team this month were busy carrying out the backfilling of the basement. The backfilling of a basement is an important step in the construction, providing vital structural stability, support to the basement walls and a barrier for external forces.

The team are close to finishing the backfilling to the basement, fire tanks, lift cores, the situ walls adjacent to the fire pump and potable water area

Register Your Interest